Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

Ways in which eutrophication can be reduced in waterways?
name three multipication problems that equal to 12
The ratio of apples to bananas in a bowl of fruit is 2:5 if there are 49 total pieces of fruit in the bowl how many are apples
branch of government that writes laws
which is the best definition of nationalism
How do I solve this
What new musical genre came about in the 1950s? A. jazz B. rock and roll C. classical D. folk music
leslie decides to join a gym she must pay a monthly fee plus a one-time fee to open a membership this situation can be modeled by the expression 55x + 80 explai
By multiplying integers what is the total of (-10)(0)
How is 90% of an organism’s used? What happens to the remaining 10% of the organism’s energy?