It takes 2 workers 6 days to paint a mansion. How many days would it take 4
workers to do the same job?

Respuesta :

dontmindme3
dontmindme3 dontmindme3
  • 01-03-2021

Answer:

2 workers = 6 days

4 workers = 3 days

Step-by-step explanation:

If it takes 2 workers 6 days, if you seep up the process with 4 workers, you would divide the days by 2 because you multilpied the workers by 2. So, it would take 3 days with 4 workers. I hope that makes sence.

Answer Link

Otras preguntas

List three reasons why Pershing was a notable leader before and during WWI.
Steven, a tailor, got an order to make a blazer. The customer specifically asked him to save 5/6 of a foot of the given cloth to make a pocket square. However,
please help and explain how u got your answer :)
The circumference of a circle is 31.4 inches. What is the circle's diameter? C=31.4 in Use 3.14 for ​.
home rule means that local governments in michigan can
Washington formed a group of advisors to help him run the country. This group was known as A. the Electoral College. B. the President’s Cabinet. C. the Senat
At the end of the nineteenth century, architects and fashion, graphic, and product designers moved away from the floral curvilinear elements of art nouveau and
what was a likely motivation to send colonists to Australia in the first place?
explain what is meant by polar molecule
On level ground, a vertical rod 12 feet tall casts a shadow 4 feet long, and at the same time a nearby vertical flagpole casts a shadow 12 feet long. how many f