The most common type of logical dependency to determine the sequence of project activities is "finish-to-finish" (FF).
a. True
b. False

Respuesta :

Limosa
Limosa Limosa
  • 15-01-2020

Answer:

Option B i.e., False is the correct option.

Explanation:

The following statement is incorrect because, It is the logical relationship not the logical dependency to recognize the series of the activity of the project details. So, that's why the following option is correct according to the given statement. the following relationship is also established between the specific schedule.

Answer Link

Otras preguntas

What is 19x - 23x ?
When did women began to fight for the right to vote during the formation of the United States?
An alternator diode is being tested using a digital multimeter set to the diode check position. A good diode will read _______ if the leads are connected one wa
Choose the ratio that is equivalent to this one: 8/1 A) 5/40 B) 40/5 C) 13/6
Please help me with this
How is C10 H16 + 8 Cl2+ 10C + 16 HCL written
Differentiating a Logarithmic Function in Exercise, find the derivative of the function. See Examples 1, 2, 3, and 4. y = ln x/x^2
A longitudinal study found that spanking before age ______ was related to behavioral problems in middle and late childhood.
Determine whether the improper integral converges or diverges, and find the value of each that converges. ∫^-1_-[infinity] ln |x| dx
THE SUM OF THE DIGITS OF A CERTAIN TWO-DIGIT NUMBER IS 13. REVERSING ITS DIGITS INCREASED THE NUMBER BY 9. WHAT IS THE NUMBER?