To complete a job a crew of 8 people needs 18 days. How long will the same job be finished if the crew will have 9 people?

Respuesta :

rockyrules789 rockyrules789
  • 01-11-2019

Answer:

16

Step-by-step explanation:

.

Answer Link
lajfoaofje lajfoaofje
  • 27-06-2020

Answer:

16

Step-by-step explanation:

Answer Link

Otras preguntas

What is the equation of this line? A. y = 2x - 3 B. y = -1/2x -3 C. y = -2x -3 D. y = 1/2x -3
What economic impact does Day of the Dead have on the floral industry in Mexico and the U.S?
According to the chart above, the largest percentage of a person’s carbon footprint comes from: a. Electricity c. Recreation and Leisure b. Food and Drink d. Ga
What type of energy does a ball falling through the air have?
This text should be in three paragraphs. Select the words where the second and third paragraphs should begin A treatment for peanut allergies using peanuts them
find the value of x , please
determine if the two triangles are congruent. if they are, state how you know.
Cardiovascular exercise involves
Who brought the samba dance to Brazil?
A theater has 384 seats. Each row has 16 seats. The area model represents this situation.What is the value of x in the area model?