A task is completed by 30 persons in 4 days. In how many days the same will be completed by 40 persons? REASON.

Respuesta :

sarajevo
sarajevo sarajevo
  • 03-08-2018

As per the given data

A task is completed by 30 persons in 4 days

we are supposed to find In how many days the same will be completed by 40 persons

Task is completed by 30 persons in 4 days, it mean

30 person does one fourth of the work in one day

1 person does [tex] \frac{1}{4*30}=\frac{1}{120}th [/tex] of the work in one day

So back to previous step,

work done by 40 person in one day =[tex] 40*\frac{1}{120} =\frac{1}{3} [/tex]

Hence the number of days required to complete the work by 40 person =3

Answer Link

Otras preguntas

When a math question asks you to write an inequality is it the expression I wrote or is it the answer I get?
What was one of president wilson four points?
Describe the land around san Antonio where we live?
Why are chromosome not visible in most cells expect during cell division?
Darwin’s theory of common descent states that all organisms _____.
Does the following represent the Substitution Property? If y = 2x and x = 6 then y = 12.
How did hitler manipulate the term aryan for nazi purposes?
Which of the following is an indicator of good water quality? (2 points) pH lower than 5.0 High levels of fecal coliformHigh levels of dissolved oxygenAll of th
Beginning with the Red Scare of the 1920s, which historical development contributed to a recurring pattern of anti-communism in the United States? A. Growing pr
what is 62.80 rounded to the nearsest hundreth