A construction contract that contains a provision requiring stipulated per diem payments to the owner for the builder's inexcusable delays in performance is said to include a clause that provides for _________________ damages.
A. Consequential damages
B. Liquidated damages
C. Punitive damages
D. Nominal damages

Respuesta :

Otras preguntas

Can someone please help Bigmamma explain the question below to my daughter. I grew up on basic Math. Please! Question- Tasha believes that she can rewrite the d
What is the value of the expression -36+7
"Do you know the name of the most famous peanut farmer in Georgia?" Is this sentence a Imperative, Exclamatory, Declarative, Interrogative?
360 customers in 30 days unit rate?
X3=512 solve each equation for x
Around 80% of India's population practices which religion?
four noncoplanar points define a space, but could they be used to form two intersecting planes? Explain why or why not
A square plot of land has a building 60ft long and 40ft wide at one corner. the rest of the land outside the building forms a parking lot. if the parking lot ar
What is greater pie of 22/7
Find four consecutive odd integers whose sum is 56