Using the PERT estimate, calculate the estimated duration of an activity given:
Optimistic Estimate = 21 days
Pessimistic Estimate = 110 days
Most Likely Estimate = 55 days
a) 62.5 days
b) 74 days
c) 65 days
d) 68.5 days