A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that...

Respuesta :

Otras preguntas

Simplify the expression to a +bi form: (-12+4i)+(2-2i)
The likelihood that Han makes a free throw in basketball is 60%. The likelihood that he makes a 3-point shot is 0.345. Which event is more likely, Han making a
New France was characterized by:
​(4x2−2x+28​)+​(4x2+4x−55​)
Divide the following and then check by multiplying. 7 483
9x+7y equation or expression?
Your employee benefits include family health care coverage. You contribute 16% of the cost. You get paid monthly and $135.00 is taken out of each paycheck for f
YEAR 8 MATHS , WILL MARK BRAINELIEST
what statement best describes the difference between a scientific theory and a scientific law
The brain is far more malleable than we think and by taking actions (using strategies,practicing, asking good questions,.) we can increase our neural growth. Th